Friday, September 26, 2025

We're Floored

Many thanks to Richard Schauer, who yesterday passed along news and some photos regarding progress on the South Storage Building that is being built for our bus departments:


I am quite happy to announce that the concrete floor has been completed on our new bus garage!  We received a very favorable bid from a local company and completed this part of the project well under the estimated cost.  Unfortunately, it appears that the electrical work, which is the only substantial work remaining before the occupancy inspection, will come in over our initial estimate; the bids are due later this week.

The attached pictures were taken today, looking in from both end doors.

This garage will give all of our trolley and motor buses an indoor home, with some space available for future expansion of our fleet as important examples come available and for storage of parts in an organized manner.  Thank you for supporting us!