36 Report

Several things were accomplished by Al Reinschmidt and me.  We drilled out rivets in several trolley poles, so that the correct harps can be installed on the two that have been selected for use on the car.  Then Al helped me mount and connect the rebuilt grid box.  I bolted both trolley bases in place.  We also tested the motor circuit.  This identified a couple of loose connections, and after some work, these were fixed.  The control circuits and motor circuits now appear to be ready for service.  I won't be able to post pictures until tomorrow.  Check back then!